Project:
|
S0103 - Reliability of distribution networks
|
|
Deliverable:
|
Report on the impact of automation on distribution
system reliability
|
|
Deliverable:
|
Specification of a reliability analysis module
|
|
Deliverable:
|
A general purpose reliability analysis module
|
|
|
|
|
Project:
|
S0104 - Modelling maintenance and replacement
policies
|
|
Deliverable:
|
Simple model illustrating different maintenance
approaches
|
|
Deliverable:
|
Detailed six stage framework to use condition
information when formulating asset management
policy.
|
|
|
|
|
Project:
|
S0105 - Distribution system state estimation
|
|
Deliverable:
|
Report on scope for state estimation in distribution
networks
|
|
|
|
|
Project:
|
S0107 - Managing extremes in network performance
|
|
Deliverable:
|
Report covering the work on extremes in network
performance caused by repeated outages and how
trends in this kind of data could be detected
|
|
|
|
|
Project:
|
S0108 - Effect of network design and automation
on customer performance
|
|
Deliverable:
|
Report describing existing practice and expectations
for automation together with an appraisal of
viable models
|
|
Deliverable:
|
Report describing improved methods for design
and automation to reduce customer interruptions
and customer minutes lost
|
|
|
|
|
Project:
|
S0109 - Assessment of strategies for improving
network performance
|
|
Deliverable:
|
Report on choice of strategies to be compared
|
|
|
|
|
Project:
|
S0110 - Evaluation of Network Voltage Levels
|
|
Deliverable:
|
Report on statistical impact on cost of uprating
distribution circuits to higher voltage levels
vs cost of increasing extent of primary network
|
|
|
|
|
Project:
|
S0112 - Understanding the customers' perception
of supply quality
|
|
Deliverable:
|
A summary report on applicable techniques and
existing techniques plus questionaire produced
for survey
|
|
Deliverable:
|
Report on the survey and appraisal of the method
|
|
|
|
|
Project:
|
S0114 - Determining how often to sample
the condition of network items
|
|
Deliverable:
|
A report providing practical guidance on how
much sampling should be carried out, of what,
and how often
|
|
|
|
|
Project:
|
S0116 - Evaluation of voltage control techniques
|
|
Deliverable:
|
Report on the scope for the application of
alternative voltage control regimes
|
|
Deliverable:
|
Report on the effect on network performance
of operating transformers on fixed tap at appropriate
voltage levels
|
|
|
|
|
Project:
|
S0121 - Survey of tools and techniques for
improving network performance
|
|
Deliverable:
|
Report on survey of requirements
|
|
|
|
|
Project:
|
S0122 - Alternative earthing techniques
: reducing customer interruptions via alternative
earthing techniques and temporary reconfiguration
of earthing
|
|
Deliverable:
|
Final report with recommendations
|
|
|
|
|
Project:
|
S0123 - Worst served customer
|
|
Deliverable:
|
Recommendations for improving service to customers
with QoS problems
|
|
|
|
|
Project:
|
S0104 - Modelling maintenance and replacement
policies
|
|
Deliverable:
|
Final report on the work including description
of the work on modelling maintenance and replacement
policies
|
|
|
|
|
Project:
|
S0108 - Effect of network design and automation
on customer performance
|
|
Deliverable:
|
Report on model for analysis of feeder for
different automation schemes for varying configurations
|
|
|
|
|
Project:
|
S0110 - Evaluation of network voltage levels
|
|
Deliverable:
|
Report
|
|
|
|
|
Project:
|
S0116 - Evaluation of voltage control techniques
|
|
Deliverable:
|
Simulations of voltage control techniques for
steering group approval; proposals for simulations
to be extended to conditions under which fixed
tap transformers can be operated; data on network
performance and cost implications
|
|
|
|
|
Project:
|
S0125 - Study to evaluate the value of lost
load
|
|
Deliverable:
|
Final report containing a summary and critique
of previous work
|
|
Deliverable:
|
Report containing the requirement specification
for establishing customer interruption costs
and methodology for calculating outage costs
to enable cost-benefit analyses
|
|
|
|
|
Project:
|
S0126 - Program to identify whether loads
can be connected to existing networks
|
|
Deliverable:
|
Specification of the functionality of the tool
and how it will assess proposed connections
|
|
Deliverable:
|
User friendly tool for assessing loads - the
tool will have the capability of linking to
company databases but no interfacing will have
been carried out
|
|
Deliverable:
|
Telephone support and site visits with a view
to encouraging the take up of the tool through
sponsored contracts
|
|
|
|
|
Project:
|
S0127 - Module 1 Administration
|
|
Deliverable:
|
Module administration service
|
|
|
|
|
Project:
|
S0128 - The identification of underlying
trends in performance
|
|
Deliverable:
|
A report highlighting the most applicable techniques
available for trend detection/elimination of
extreme events, and examples of their application
|
|
|
|
|
Project:
|
S0129 - Define what is an acceptable supply
quality to the customer
|
|
Deliverable:
|
Interim report detailing the progress made
|
|
|
|
|
Project:
|
S0130 - Influence of Duos on earning potential
of networks
|
|
Deliverable:
|
Focused report on the findings
|
|
Deliverable:
|
Excel spreadsheet for comparing Duos charges
and network expenditure
|
|
|
|
|
Project:
|
S0131 - Embedded generation and system security
|
|
Deliverable:
|
Final report containing an investigation of
the impact of embedded generation on system
security, hand calculations and suggestions
for future work
|
|
Deliverable:
|
Presentation to module 5 steering group
|
|
Deliverable:
|
Final report detailing results of investigations
and the experiences of distributors world-wide
|
|
|
|
|
Project:
|
S0137 - Customer quality of supply as a
function of protection and autoreclosing policies
|
|
Deliverable:
|
Report detailing how faster protection and
switchgear operating times affect network performance
|
|
|
|
|
Project:
|
S0138 - Effects of fault clearance times
on customer quality of supply
|
|
Deliverable:
|
Report detailing the findings of the investigation
|
|
|
|
|
Project:
|
S0140 - Economics of distribution networks
|
|
Deliverable:
|
Report indicating the network elements where
an increased capital investment aiming to reduce
losses would have the greatest cost-benefit
|
|
|
|
|
Project:
|
S0141 - The effect on reliability of least
cost design options
|
|
Deliverable:
|
A user friendly software tool that will enable
the user to examine different design policies
|
|
|
|
|
Project:
|
S0142 - Performance measures
|
|
Deliverable:
|
Document findings
|
|
|
|
|
Project:
|
S0108 - Effect of network design and automation
on customer performance
|
|
Deliverable:
|
Summary report of PhD thesis highlights
|
|
|
|
|
Project:
|
S0110 - Evaluation of network voltage levels
|
|
Deliverable:
|
Report detailing the findings of the further
studies
|
|
|
|
|
Project:
|
S0125 - Study to evaluate the value of lost
load
|
|
Deliverable:
|
Report containing the conclusions from the
case study
|
|
|
|
|
Project:
|
S0129 - Define what is an acceptable supply
quality to the customer
|
|
Deliverable:
|
A report on the survey collation
|
|
|
|
|
Project:
|
S0138 - Effects of fault clearance times
on customer quality of supply
|
|
Deliverable:
|
Report detailing the findings of the investigation
|
|
|
|
|
Project:
|
S0139 - Implementing impedance earthing
|
|
Deliverable:
|
A report on the implementation of impedance
earthing
|
|
|
|
|
Project:
|
S0140 - Economics of distribution networks
|
|
Deliverable:
|
Report indicating the network elements where
an increased capital investment aiming to reduce
losses would have the greatest cost-benefit
|
|
|
|
|
Project:
|
S0142 - Performance measures
|
|
Deliverable:
|
Document findings
|
|
|
|
|
Project:
|
S0143 - Spreadsheet to assist understanding
of power systems components
|
|
Deliverable:
|
Two Excel 95 spreadsheets and algorithm documentation
|
|
|
|
|
Project:
|
S0146 - Environmental impact of network
design
|
|
Deliverable:
|
Report on highest risk areas of environmental
pressure
|
|
|
|
|
Project:
|
S0147 - Module 1 Administration 1999/2000
|
|
Deliverable:
|
Module administration service
|
|
|
|
|
Project:
|
S0149 - Module 1 Strategy Review
|
|
Deliverable:
|
Strategy review paper
|
|
Deliverable:
|
Gap identification paper
|
|
Deliverable:
|
Proposals for May 18/19 steering group meeting
|
|
|
|
|
Project:
|
S0150 - Future-proofing network investment
|
|
Deliverable:
|
Critical review of the literature and plans
for further projects
|
|
|
|
|
Project:
|
S0151 - Connecting loads to existing HV
and LV networks
|
|
Deliverable:
|
Demonstration software that provides load acceptance
at LV and HV
|
|
|
|
|
Project:
|
S0152 - Risk - Longer Term Research
|
|
Deliverable:
|
Report detailing risk analysis methodologies,
prototype software and a worked real world example
|
|
|
|
|
Project:
|
S0153 (Module 5 part is S0543)
|
|
Deliverable:
|
Obtaining benefits from the connection of embedded
generation
|
|
Project:
|
S0151 - Connecting loads to existing HV
and LV networks
(Stage 3)
|
|
Deliverable:
|
Demonstration software which looks at harmonic
connection of loads
|
|
|
|
|
Project:
|
S0152 - Risk - Longer Term Research
|
|
Deliverable:
|
Report detailing initial development of methodologies
|
|
Deliverable:
|
Report detailing further development of methodologies
|
|
Deliverable:
|
Report describing the findings
|
|
Deliverable:
|
Briefing paper/Half-day seminar
|
|
|
|
|
Project:
|
S0153 - Obtaining benefits from the connection
of embedded generation
|
|
Deliverable:
|
Specification for multi-criteria decision support
tool
|
|
|
|
|
Project:
|
S0156
- Measuring against normalised weather |
|
Deliverable:
|
A report highlighting the most applicable techniques
including extreme events
|
|
|
|
|
Project:
|
S0159
- Reshaping 11kV rural networks for reliable operation |
|
Deliverable:
|
Report analysing whether current 11kV rural
network designs/shapes can meet the new Standard
|
|
|
|
|
Project:
|
S0160
- World-wide review of 11kV urban network design |
|
Deliverable:
|
Critical review of the literature and plans
for further projects
|
|
Deliverable:
|
Report defining criteria for more cost effective
urban system
|
|
Deliverable:
|
Stage 2 report
|